1517 San Jacinto St.; Houston, Texas, 77002
phone 713-652-3937 | 800-423-1825
fax 713-652-1914 | 713-652-1911
This standard focuses on the direct design of buried precast concrete pipe using Standard Installations, and reviews the design and construction of the soil/pipe interaction system that is used for the conveyance of sewage, industrial wastes, storm water, and drainage. To account for the interaction between pipe and soil envelope when determining loads, pressure distributions, moment, thrust and shear, the volume presents the SIDD method for buried precast concrete pipe. Excavation, safety, foundation, bedding, sheathing removal and trench shield advancement are among those construction requirements for precast concrete pipe designed by the SIDD method that are presented here.